Aries Marine and Engineering Services

DESIGN PROJECTS

FEED study of oil terminals in Iraq
  • Global Analysis
  • Damage Analysis
  • Modelling and site survey to incorporate the actual damages in the model
  • Largest Accidental Load Limit State in Middle East
 
Conversion of Ro-Ro vessel to Cable Laying Ship
  • Vessel aft to be cropped off and new aft structure for thrusters.
  • The total LBP of the vessel after rebuilding the aft end should be less than 125m
  • Three Nos Cable holds of diameter 14m and capacity 700 cu-m each.
  • New deck houses on the aft end for accommodating Cable highway, ROV & Umbilical winch, CDE/Diverters, ROV, CDE & Plough control rooms.
  • An additional deck house introduced on top of the existing forward accommodation block to increase the crew capacity.
  • Accommodation up gradation for 72Complement with SPS notation.
  • A-frame, plough, Stonker, LCE installed on the aft end of the vessel for facilitating cable laying operation.
  • An A-Frame, ROV and an ROV operational winch need to be installed at midship.
  • A CDE unit and diverters installed on Fwd deck for Cable Repair operation.
  • Intact stability – IS code 2008
  • Probabilistic damage stability as per SOLAS 2009
  • Bottom damage stability as per regulation 9 – SOLAS 2009
  • Stability during crane operation and during ROV operation
  • Cable hold capacity – up to 2950t
 
 
 
 

Sea Transportation of World's largest Turret

  • Transportation of 3500T of steel from Dubai to Korea
  • Turret Module of the world’s largest FLNG
  • Analysis including Deck Strength, Global Deflection Analysis, Ballasting Sequence, Loadout Manual, Mooring Arrangement etc.
Medusa Spar hull: Load Out in progress
edusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 

Conversion of tanker to FSO

  • Helideck Installation.
  • Fiscal Metering Package
  • Crude Oil Cargo handling System.
  • Structural Steel Upgrade.
  • Global Strength Analysis
  • Dropped Object/Slamming/Sloshing analysis
  • Fatigue analysis
  • Green Sea Analysis
  • Living Quarter Upgrade
  • Mooring – Bow and Tandem Mooring
  • Bow and Tandem Offloading
  • Electrical load analysis
  • Lighting layout
  • Inclining Experiment and Stability
  • Installation and commissioning of H2S, LEL alarms, CCTV
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
Medusa Spar hull: Load Out in progress
 
Medusa Spar hull: Load Out in progress
 

Design of topside accomodation module for FSO

  • Engineering for Accommodation Module/Helideck
  • Clients : Chalmers / Yinson/ Eni
  • Scopes includes Design of new accommodation modules, Inplace Analysis, Lifting Analysis, Fatigue Analysis, Accidental Load Analysis, etc
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
 

LBD100 – Liftboat for operation in 100m water depth

  • Engineering for the world’s deepest liftboat
  • Project FEED and feasibility assessment completed
  • Detail Engineering for class of sister liftboats
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
Medusa spar: after deck installation
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 

Site specific assessment of jack up rigs

  • Site specific Global assessment.
  • Site specific fatigue life estimation
  • Modelling as per actuals incorporating UT thickness reports.
  • FEA of Cantilever substructure for updated drilling loads.
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
Medusa spar: after deck installation
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 

FEA,Strength analysis,deflection checks

  • Refurbishment and upgradation at Lamprell on 2014.
  • Upgradation of both starboard and port side cranes
  • Port side crane on a 11m high pedestal
  • Starboard side crane on a pedestal connected onto the starboard jack casing
  • FEA of both structures including FEA of Jack casing for the jacking loads and the crane loads.
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
Medusa spar: after deck installation
 
Medusa Spar hull: Load Out in progress
 

SEU Complete Design Solution

  • Initial FEED and feasibility.
  • Detail design
  • Complete project execution.
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
Medusa spar: after deck installation
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 

FEM Analysis

  • RIG DIYINA - Spud Can Analysis For Docking.
  • ALPHA KENYA - Spud Can Analysis.
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
 
Medusa spar: after deck installation
Medusa Spar hull: Load Out in progress