Aries Marine and Engineering Services

DESIGN PROJECTS

FEED study of oil terminals in Iraq
  • Global Analysis
  • Damage Analysis
  • Modelling and site survey to incorporate the actual damages in the model
  • Largest Accidental Load Limit State in Middle East
Marine consultants in UAE
Aries Naval Architects
 
Conversion of Ro-Ro vessel to Cable Laying Ship
  • Vessel aft to be cropped off and new aft structure for thrusters.
  • The total LBP of the vessel after rebuilding the aft end should be less than 125m
  • Three Nos Cable holds of diameter 14m and capacity 700 cu-m each.
  • New deck houses on the aft end for accommodating Cable highway, ROV & Umbilical winch, CDE/Diverters, ROV, CDE & Plough control rooms.
  • An additional deck house introduced on top of the existing forward accommodation block to increase the crew capacity.
  • Accommodation up gradation for 72Complement with SPS notation.
  • A-frame, plough, Stonker, LCE installed on the aft end of the vessel for facilitating cable laying operation.
  • An A-Frame, ROV and an ROV operational winch need to be installed at midship.
  • A CDE unit and diverters installed on Fwd deck for Cable Repair operation.
  • Intact stability – IS code 2008
  • Probabilistic damage stability as per SOLAS 2009
  • Bottom damage stability as per regulation 9 – SOLAS 2009
  • Stability during crane operation and during ROV operation
  • Cable hold capacity – up to 2950t
Marine consultants in UAE
Aries Marine consultants in UAE
Naval Architects in UAE
 
Naval Architects
Aries Marine Naval Architects project
Naval Architects company Design
 
Design projects of Marine engineering
Navel design projects - Aries marine
 
 

Sea Transportation of World's largest Turret

  • Transportation of 3500T of steel from Dubai to Korea
  • Turret Module of the world’s largest FLNG
  • Analysis including Deck Strength, Global Deflection Analysis, Ballasting Sequence, Loadout Manual, Mooring Arrangement etc.
Medusa Spar hull: Load Out in progress
edusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 

Conversion of tanker to FSO

  • Helideck Installation.
  • Fiscal Metering Package
  • Crude Oil Cargo handling System.
  • Structural Steel Upgrade.
  • Global Strength Analysis
  • Dropped Object/Slamming/Sloshing analysis
  • Fatigue analysis
  • Green Sea Analysis
  • Living Quarter Upgrade
  • Mooring – Bow and Tandem Mooring
  • Bow and Tandem Offloading
  • Electrical load analysis
  • Lighting layout
  • Inclining Experiment and Stability
  • Installation and commissioning of H2S, LEL alarms, CCTV
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
Medusa Spar hull: Load Out in progress
 
Medusa Spar hull: Load Out in progress
 

Design of topside accomodation module for FSO

  • Engineering for Accommodation Module/Helideck
  • Clients : Chalmers / Yinson/ Eni
  • Scopes includes Design of new accommodation modules, Inplace Analysis, Lifting Analysis, Fatigue Analysis, Accidental Load Analysis, etc
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
 

LBD100 – Liftboat for operation in 100m water depth

  • Engineering for the world’s deepest liftboat
  • Project FEED and feasibility assessment completed
  • Detail Engineering for class of sister liftboats
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
Medusa spar: after deck installation
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 

Site specific assessment of jack up rigs

  • Site specific Global assessment.
  • Site specific fatigue life estimation
  • Modelling as per actuals incorporating UT thickness reports.
  • FEA of Cantilever substructure for updated drilling loads.
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
Medusa spar: after deck installation
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 

FEA,Strength analysis,deflection checks

  • Refurbishment and upgradation at Lamprell on 2014.
  • Upgradation of both starboard and port side cranes
  • Port side crane on a 11m high pedestal
  • Starboard side crane on a pedestal connected onto the starboard jack casing
  • FEA of both structures including FEA of Jack casing for the jacking loads and the crane loads.
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
Medusa spar: after deck installation
 
Medusa Spar hull: Load Out in progress
 

SEU Complete Design Solution

  • Initial FEED and feasibility.
  • Detail design
  • Complete project execution.
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
Medusa spar: after deck installation
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 
Medusa Spar hull: Load Out in progress
Medusa Spar hull: Load Out in progress
 

FEM Analysis

  • RIG DIYINA - Spud Can Analysis For Docking.
  • ALPHA KENYA - Spud Can Analysis.
Medusa Spar hull: Load Out in progress
Medusa spar: after deck installation
 
Medusa spar: after deck installation
Medusa Spar hull: Load Out in progress